Braving the “high-temperature baking” season, construction of the external tanks for the Andefu project is nearing completion.
Release time:
2025-07-15
Today, we’re launching... The third installment of the “Let the Lens Enter the Air Separation Frontline” series—“Fighting Through the ‘High-Temperature’ Season: Construction of the External Tanks for the Andefu Project Is Nearing Completion.”

Just as the drumbeat of the college entrance examination has faded, midsummer arrives, sweeping across the land with sweltering heatwaves. In the scorching city of Nanjing, at the site of the Jiangsu Andefu 49,000 m³ cryogenic liquid ammonia storage tank and supporting facilities project—undertaken by China Air Separation—the fiery “high-temperature baking” season has officially begun. The project’s frontline workers, undaunted by the intense heat, are racing against time to deliver a stellar engineering masterpiece. Currently, construction of the outer tank is nearing successful completion!
Pioneers lead the way, racing against time.
Since the start of construction last October, the Andefu Project has established the “Andefu Low-Temperature Liquid Ammonia Project Party Member Pioneer Team” to harness the power of the Party as a driving force and propel project development forward. Under the exemplary leadership of the Party Member Pioneer Team, all members have united as one and fought vigorously, completing the foundation pouring for the low-temperature liquid ammonia storage tanks ahead of the Spring Festival. As the new year begins, the project shows no signs of slowing down: in March, it entered the tank installation phase; by May, all pile foundation work had been completed. Currently, construction of the outer tank is nearing completion, while civil engineering and pipeline system installation are simultaneously progressing at full speed, with all efforts focused on achieving the mid-year handover target by the end of December.

Fighting bravely against the high temperatures, unafraid of the “roasting” test.

Recently, as temperatures in Nanjing have been steadily rising, the surface temperature at construction sites has already exceeded 50°C. The scorching sunlight is baking rebar and steel plates, making even the air feel unbearably hot. At the site, project personnel are fully focused on their work. Welding of the wall panel circumferential weld seam The welding torch spewed scorching flames, and sparks flew everywhere. Meanwhile, the inspectors carried out their work with meticulous care. Visual Quality Inspection of Tank Wall Plate Welds Ensuring that every weld meets the highest standards. At the same time, they braved the scorching heat and carefully... Inspect the temporary electrical wiring inside the liquid ammonia storage tank. Ensure the safety of construction power supply.

On the other side, Weighbridge foundation Construction is also in full swing, with workers bending low to work under the scorching heat. Rebar tying and formwork support acceptance Sweat kept dripping down along the straps of the hard hat. Meanwhile, in the outer tank operation area, welders were busy carrying out... Welding of vertical weld seams on the outer tank wall panels Under their heavy protective suits, their clothes were already soaked through, yet they remained fully focused, meticulously completing each and every step of the process.

Under scientific management and highly efficient collaboration, the Andefu project is steadily advancing, fully committed to meeting the mid-December handover target. Their steadfast dedication amid scorching heat not only ensures the project’s progress but also vividly embodies the selfless devotion of frontline builders. Their figures are the most moving sight; their sweat is the strongest guarantee. Let us pay tribute to these fearless fighters who brave the intense heat and labor tirelessly on the front lines!